Kırka Boron Operations MV Infrastructure

MV Electrical & Infrastructure Works in Various Regions

Kırka MV Electrical Infrastructure Project

Project Overview

Emit was contracted directly by Eti Maden to undertake a critical infrastructure project involving the construction of 5 Medium Voltage (MV) transformer substations, along with associated Low Voltage (LV) distribution, site lighting, and electrical infrastructure across various areas of the Kırka Boron Operations facility.

Scope of Work & Key Deliverables

The project scope included the supply, installation, and commissioning of the following key components:

  • MV Switchgear: 5 units of 12 kV Medium Voltage cells.
  • MV Cabling: 7,150 meters of Medium Voltage underground cable.
  • Transformers: Supply and installation of 2 new 1000 kVA dry-type transformers, plus the dismantling, maintenance, and re-installation of three existing transformers (1250 kVA and 400 kVA).
  • Substations: 5 reinforced concrete kiosks to house the transformer substations.
  • LV Systems: Complete installation of high-current power and lighting distribution systems.
  • Panel Manufacturing: Supply and installation of Main Distribution Panels (ADP), power, and lighting panels.